Longside Wood, Ramsgill - Wednesday 12 November 2014



On a rather wet morning a team of six gathered to commence our new project for David Brown, the farmer at Longside, rebuilding a cheek end and repairs to a couple of gaps in a wall further along the Nidderdale Way towards Lofthouse.  

Whilst Catriona, Graham, Paul and Roger concentrated on this wall, Barry and Tony walked over to Longside Wood to put the finishing touches to the long and winding wall.


The foundations are put in place for the cheek end against the new fence post
 

At coffee break, Barry outlines a future task at the new nesting bank for sand martins which he proposed to visit after lunch. 


Meanwhile back at Longside Wood  

The cheek end of the downhill wall is in need of attention before we finally leave
Barry shelters from the rain after placing the last top stone on the Longside Wood wall.
 A total of 21 gaps completed over 12 weekly visits.  

With the rain becoming heavier it was decided to rejoin the rest of the team for lunch 

  
 Only to find they had already departed for a drier location to where we do not know.


Barry and Tony decided to adjourn from any further walling for the day and scope the task at the sand martin nesting bank site at Gouthwaite.




Thursday, 6 November 2014

Longside Wood, Ramsgill - Wednesday 5 November 2014



After missing a week due to team commitments elsewhere (and of course it was half term week) it was back to try and complete the last gap.  In addition to Barry, Catriona, Chris, Paul, Richard H, Roderick, Roger and Tony, we were also joined by Robert and Mark from Thorndene Forestry Services (who were having a rest day from their tree planting work and wanted to have a go at walling).

 The advance party get to work on dismantling the last section (commonly known as gaps 19 to 21) 
Robert and Mark look on and wonder whether they made the right choice to try walling

Reinforcements start to arrive 
  
Under the guidance of Chris, Robert and Mark are soon getting familiar with the procedure

Barry and Paul make a start on rebuilding the gap just before the hand gate 
 

 … and the finished job


 Back at the far end of the wall it is time for a lunch break


Just one more course to complete

                                                           
The final tidy up begins 

The long and winding wall is nearly finished – we just need to find some more top stones to make it complete


Tony